Thursday, July 21, 2011

Nicki’s Field Study, phase 1: the art of doing (and redoing!)

Late last week the Water Resource Engineering team completed the first phase of the field plot study site preparation.






With all hands on deck (at one time or another), by mid-day Thursday, what began as a pristine 4620 sq. ft (or ~429 sq. m) piece of land, had taken the form of 16 15’X15’ square plots with the beginnings of irrigation pipe running to each square.




Day 1: and you will know us by our trail of markings…and re-markings


The first day’s objective was to bring to life the plot that had until then existed only as an intricately detailed design and specs graphic.



Despite our best efforts, however, we soon learned that measuring and marking a perfect square on a well-worn field plot is a rather complicated affair.






Eventually, we discovered the utility of a time-saving tool invented some time ago: the right angle! First, Isaya’s version, combining both ancient geometry and measuring tapes.


Later, the actual physical incarnation came into play. This certainly sped up the process of measuring proper lengths.



For each length, rebar was hammered into the ground at each end, string attached, and paint sprayed along the distance.



In addition, thanks to some on-the-fly redesign work courtesy of Tina, who saw past the old assumptions of valve location, inter-plot marking work was streamlined and allowed us to leave a more-or-less accurately marked field plot ready for trenching by day’s end .

Pipes arrive at mid-day.


Day 2: let the stormy clouds chase, everyone from the place…(except Manny!)



Manny in medias res on trench day


Day 2’s objective – trench for the plot’s main water line, for the 16 rep water lines and for the future timer power supply. Drafted into the Water Resource Team’s ranks for the day, for his skill with a trencher and his ability to keep cool before seemingly insurmountable obstacles, intrepid TREC field crew member Manny Soto!


The trencher kept us plenty busy – we shoveled loose soil left in its wake and leveled out live wire and water line areas where it could not enter.




Soon after mid-day, the rain clouds rolled in, but that didn’t stop Manny. He simply broke out his large umbrella and continued on, trenching line after line until the entire area was finished and ready for the pipe to be laid for 16 plots! THANK YOU, Manny!



Day 3: Nicki’s birthday! (oh yeah…pipe-laying day)



Could there be a better way to commemorate 23 years on the planet than cutting and gluing PVC pipe in 90+ degree heat?




The PVC pipe (1.5” for the main line and ¾” for the secondary lines to the plots) was laid out next to the trenches, cut, glued, and placed in the trenches. The main line was installed first, and then the secondary lines, beginning with the plots furthest from the main line.






After all of the pieces (pipe, elbows, & tees) for each plot were glued together, they were placed in the trenches and the pipe was labeled for each plot.



Next step: Phase 2

· Finish building and test lysimeter prototype
· Piecing together water-meter/valve/pressure gage set-ups in the lab


Acknowledgments



I cannot thank everyone (Manny, Jorge, Mike, Isaya, David, Tina, Teresa, and Dr. Kati) enough for all of the hard work and effort put into making this plot study (once only a sketch) an actual reality! Even the simplest things on paper take so much effort to actually make happen! In the end, it will all be worth it! I know it’ll be the prettiest lil’ piece of grass at TREC!


Nicole Dobbs

Monday, July 18, 2011

NSF REU in Homestead - part2!

Early last week, as part of their whirlwind tour of Florida, this summer’s NSF Research Experience for Undergraduates students (REU), including our very own Kaileigh Calhoun, visited Homestead.



UF - TREC


Their time in town included several stops. First, since the REU program’s focus is on water resources, the students learned of several relevant projects in the Water Resource Engineering and Soil Science programs here at TREC from Dr. Kati Migliaccio, PhD candidate Isaya Kisekka, and Dr. Yuncong Li respectively.






Costa Farms




The students then visited Costa Farms, a large area nursery, to learn about how water resource technology is applied in a successful commercial operation.



Jorge Bernal, et al. were kind enough to lead informative tours of the nursery’s different departments.










Miami-Dade Extension




Following lunch in downtown Homestead, the students stopped at Miami-Dade Extension for a brief introduction to the Extension concept courtesy of agent Mary McCready, who drove home the message that a viable Extension Service is essential to linking academic research and expertise with the local community.


C-111

The REU students' Homestead visit closed with a stop at the C-111 canal.





Once again, Dr. Migliaccio and Isaya briefed the students on the significance of the location with respect to SFWMD’s work there and how Isaya’s research near the C-111 relates to that work.




Cruelest month: August

With roughly two weeks left in the REU program, students in the various study sites around the state are buckling down and putting the final touches on their projects.



Kaileigh, gracing the Water Resource team since early June, has been the very picture of contented industry with her project reconciling Snapper Creek site data. Stay tuned for her exit presentation and video!

Friday, July 15, 2011

NSF REU visit










I am sure Mike or Kaileigh will post something much more eloquent - but I wanted to put a few pics out! Here are a few memories from Monday's REU tour. Thanks to everyone for your help in putting it together!! Kailiegh will only be with us 2 more weeks! Time flies! We will miss her!